Major Progress in Manmad-Jalgaon-Bhusawal 3rd Line Project

In a significant development, the Manmad-Jalgaon-Bhusawal 3rd line project is making remarkable strides towards completion, marking a major boost in railway infrastructure. Here are the key highlights:

Length and Completion: The total length of this critical railway project stands at an impressive 183.94 kilometers. As of now, approximately 96.81 kilometers have been successfully completed, constituting 53% of the entire length.

Financial Investment: The project comes with a total estimated cost of 1360.16 Crores. An expenditure of 1286.75 Crores has been incurred to date, accounting for an impressive 94% of the allocated budget.

Overall Progress: The overall physical progress of the project stands at a commendable 80%, showcasing dedicated efforts and efficient execution.

Land Acquisition: The crucial process of land acquisition is well underway, with 28.19 out of 37.08 hectares already secured, marking an impressive 76% completion rate.

Completed Sections: Three crucial sections of the project have been successfully completed, covering 96.81 kilometers (53%):

  • Bhusawal-Jalgaon
  • Jalgaon-Pachora
  • Manmad-Nandgaon

Near Completion Sections: Another section, Chalisgaon-Pimparkhed, is nearing completion and is expected to be finished within this fiscal year, covering 31.79 kilometers (17%).

Sections in Progress: Two significant sections, Pachora-Chalisgaon and Nandgaon-Pimparkhed, are actively in progress, encompassing 55.34 kilometers (30%) of the project’s total length.

Key Completed Works: Several critical project components have seen substantial progress, including:

  • Earthwork, with 57% completion (34.10 out of 59.92 Lakh Cum)
  • Blanketing, with 1 Lakh Cum completed out of 7.42 Lakh Cum
  • Major bridges, achieving 50% completion with 11 out of 22 bridges finished
  • Minor bridges/RUB, with a notable 48.13% completion (142 out of 295)
  • Station buildings, reaching 47% completion (7 out of 15)
  • Track linking, with 43% completion (70 out of 160 kilometers)
  • Ballast supply, where 57% has been accomplished (2.87 out of 5.02 Lakh Cum)
  • OHE Foundations, with 24% completion (774 out of 3168)
  • Mast erection, achieving 21% completion (513 out of 2443)
  • Electrification work is progressing simultaneously with track work, ensuring a comprehensive and efficient railway system.

The Manmad-Jalgaon-Bhusawal 3rd line project signifies a significant leap forward in railway infrastructure, offering enhanced connectivity and efficiency in the region. As the project continues to progress at an impressive pace, it holds the promise of improved transportation and economic development for the area it serves.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.