Nagpur Station Redevelopment: Rail Land Development Authority (RLDA) Undertakes Ambitious Project at a Cost of 487.77 Crores

In a significant development, the Nagpur railway station is set for a major facelift as the Rail Land Development Authority (RLDA) takes charge of the ambitious redevelopment project, allocating a budget of 487.77 crores for the endeavor.

Completed Milestones:

  • Soil Investigation: Comprehensive soil investigation has been successfully concluded.
  • Site Lab Commissioned: A state-of-the-art site laboratory has been commissioned to ensure precision in construction.
  • Batching Plant Installation: The installation and commissioning of a batching plant have been completed.
  • Utility Shifting on East Side: Successful completion of utility shifting on the east side of the station.
  • Infrastructure Enhancements: Key infrastructure enhancements, including the establishment of milk siding, parking areas, and a new entry/exit for traffic diversion, have been accomplished.
  • Wheel Washing Unit Installation: The installation of a wheel washing unit, vital for maintenance, has been completed.
  • Ticket Counter Shift: A partition wall facilitating the relocation of the ticket counter has been successfully constructed.
  • Approval of Plans: The Emergency Management Plan (EMP) has been approved, and the Design Basis Report (DBR) for the building structure has received official approval.
  • EW1 Progress: Foundation work for EW1 is 98% complete.
  • Column Casting and Retaining Wall: The casting of columns and the construction of retaining walls have been completed to 100% satisfaction.
  • EW2 Advancements: For EW2, the shifting of utilities is complete, and excavation for the basement area is 90% done.

Ongoing Works:

  • EW-1 Basement Slab Casting: Currently, the casting of the basement slab for EW-1 is 80% complete.
  • Ground Floor Construction: Ground floor column casting is 40% complete, with ongoing work on shuttering and reinforcement binding for the ground floor slab (40%).
  • PCC Progress: Progress stands at 60% for Plain Cement Concrete (PCC), 60% for footing, 40% for the retaining wall, and 50% for column casting.
  • Stitch Slab Casting: The casting of the stitch slab is underway, with completion at 30%.
  • WW4 Developments: Excavation work for WW4 is progressing at 60%, PCC work is 50% complete, and the bottom raft is 50% constructed.

The Indian Railways remains steadfast in its commitment to providing enhanced facilities for passengers, and the redevelopment of Nagpur station stands as a testament to this commitment. The ongoing and completed works signify a significant step toward achieving the envisioned transformation of the railway infrastructure in the region.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.