Hassan Yard Revamp Successfully Completed Through Tireless Efforts of Mysuru Division Teams
In a remarkable achievement, the re-modelled Hassan yard was officially commissioned on December 21, 2023, at 19:30 hrs, reflecting the culmination of meticulous planning and exemplary coordination.
The transformation of the Hassan yard was made possible due to the dedicated efforts of various teams within Mysuru Division, including Engineering, GatiShakti, Signal & Telecommunication (S&T), Track Renewal Department (TRD), and Operating teams. The collaborative work, marked by day-and-night efforts, has garnered high appreciation and commendation.
The comprehensive overhaul, completed in a swift timeline, involved five days of Pre Non-Interlocking (NI) activities, including two days dedicated to regrading the existing Bengaluru line, followed by three days of Non-Interlocking work. This complex and time-sensitive project showcases the commitment and efficiency of the teams involved.
The successful commissioning of the re-modelled Hassan yard underscores the prowess of integrated planning and execution within the railway division, contributing to enhanced operational capabilities and infrastructure improvements. The accomplishment stands as a testament to the dedication and professionalism of the Mysuru Division teams.