Important Achievements regarding New Rail Line, Gauge Conversion & Doubling Projects during FY 19-20 (upto Jan 2020)
Highlights of proposed Budget FY 20-21
Andhra Pradesh:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- 113 Km long New Line Port connectivity project in Andhra Pradesh, costing Rs.2200 Cr. connecting main land with Krishnapatnam port got completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
03 Projects of total 1164 Km length, costing Rs. 11640 Cr. have been included as per below details:
- Doubling of Dharmavaram- Pakala- Katpadi of Length 290 Km, Costing ₹2900 Cr.
- Doubling of Guntur- Bibinagar of Length 248 Km, Costing ₹2480 Cr.
- Doubling of Akola- Dhone via Purna, Mudhkhed, Secunderabad, Mehboobnagar excluding Purna-Mudkhed and Bolarum-Mehboobnagar including Dhone bye pass of Length 626 Km, Costing ₹6260 Cr.
Survey works included in Budget Booklet 2020-21:
- RET survey of new line between Muddanuru to Mudigubba – 65 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
454% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4910 Cr/ Rs. 886 Cr.)
Assam & NE Region:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
02 Projects of total 157 Km length, costing Rs. 4058 Cr. have been commissioned as per below details:
- 45 Km long length doubling project from Lumding to Hojai, costing Rs.651 cr.got completed & commissioned.
- 112 Km long New line NATIONAL PROJECT construction in Tripura State named Agartala–Sabroom,costing Rs.3407 cr. got completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
- Doubling of Lumding- Tinsukia Jn- Dibrugarh of Length 381 Km, Costing ₹3810 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
120% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4669 Cr/ Rs. 2122 Cr.)
Bihar:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
04 Projects of total 139 Km length, costing Rs. 1318 Cr. have been commissioned as per below details:
- 10.7 Km long bypass line from Chhapra Gramin to Khairali got completed & commissioned in all respect.
- 67 Km long New Line project from Rajgir-Hisua-Tilaiya including Islampur-Nateshar costing, Rs.726 Cr. got completed & commissioned in all respect.
- 42 Km long Doubling project from Hajipur-Ramdayalu Nagar costing, Rs.367 cr. got completed & commissioned in all respect.
- 19 Km long Coal project named Bakhtiyarpur-Barhgot Completed and commissioned for facilitating the coal movement to Barh NTPC Thermal Power House
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
05 Projects of total452 Km length, costing Rs. 4908 Cr. have been included as per below details:
- Doubling of Narkatiaganj- Raxaul- Sitamarhi- Darbhanga & Sitamarhi- Muzaffarpur of Length 255.5 Km, Costing ₹2555 Cr.
- Doubling of Katihar- Kumedpur and Katihar- Mukuria of Length 64.5 Km, Costing ₹645 Cr.
- Barauni- Bachwara 3rd& 4th line of Length 32 Km, Costing ₹590 Cr.
- Sonenagar bye pass line from Chiralapothu to Bagha Bishunpur, Costing ₹125.5 Cr.
- Doubling of Gorakhpur- Valmikinagar of Length 87 Km, Costing ₹992.7 Cr.
Survey works included in Budget Booklet 2020-21:
- FLS of Raxaul-Kathmandu new electrified rail link (Funded by MEA)- 136 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
297% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4497 Cr/ Rs. 1132 Cr.)
Chhattisgarh:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- 42.5 Km long New Line Coal Project from Kharsia-Korichhapar completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
- Doubling of Boridand- Ambikapur and Boridand- Chirmiri of Length 148.2 Km, Costing ₹1482 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
1352% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4515 Cr/ Rs. 311 Cr.)
Delhi:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- Long pending Doubling project (7 Km length but very important to decongest New Delhi Station) between New Delhi to Tilkar Bridge(5th& 6th line), costing Rs.137 cr. has been commissioned.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
225% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 312 Cr/ Rs. 96 Cr.)
Gujarat:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- 24 Km long Doubling project from Abu Road to Sarotra Road, costing Rs.131 cr. completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
- Doubling of Bhatinda- Bhildi via Sirsa, Hisar, Ratangarh, Degana, Luni, Samdhari excluding Degana- Rai ka Bag of Length 752.2 Km, Costing ₹7522 Cr
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
591% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4072 Cr/ Rs. 589 Cr.)
Goa:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
Chandargaon- Cansaulium Rail Flyover of Length 16 Km, Costing ₹1892 Cr
Haryana:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- 320 Km long Gauge Conversion Project from Jaipur-Ringus-Sikar-Churu & Sikar-Loharu, costing Rs.1116 cr. got completed & commissioned in all respect.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
05 Projects of total 1,071 Km length, costing Rs. 10,742 Cr. have been included, as per below details:
- Doubling of Panipat- Rohtak of Length 71.4 Km, Costing ₹714 Cr.
- Doubling of Firozpur- Bhatinda and Jakhal- Hisar of Length 168.8 Km, Costing ₹1688 Cr
- Doubling of Asthalbohar- Rewari of Length 75.2 Km, Costing ₹752 Cr.
- Doubling of Bhatinda- Bhildi via Sirsa, Hisar, Ratangarh, Degana, Luni, Samdhari excluding Degana- Rai ka Bag of Length 752.2 Km, Costing ₹7522 Cr.
- Connectivity between Palwal (IR) and New Prithala (WDFC) of Length 3.5 Km, Costing ₹65.75 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
240% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 1070 Cr/ Rs. 315 Cr.)
Himachal Pradesh:
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
453% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 597 Cr/ Rs. 108 Cr.)
Jammu & Kashmir:
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
273% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 3895 Cr/ Rs. 1044 Cr.)
Jharkhand:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
05 Projects of total 141 Km length, costing Rs. 1425 Cr. have been included, as per below details:
- Doubling of Pradhan Kuntha Jn– Pathardih Bazar– Bhojudih of Length 17.1 Km, Costing ₹171 Cr.
- Doubling of Muri- Barkakhana of Length 58 Km, Costing ₹580 Cr.
- Permanent diversion of fire affected Dhanbad- Chandrapura line by Dhanbad- Ispatnagar line via Telulmari, Nichitpur, Matari, Telo including Y connection at Dhanbad and Ispatnagar of Length 43.8 Km, Costing ₹438 Cr.
- Madhupur bye-pass line, costing ₹106.5 Cr.
- Doubling between Bhojudi- Talgoria in connection with permanent diversion of fire affected Dhanbad- Chandrapura line of Length 12.5 Km, Costing ₹129 Cr.
Survey works included in Budget Booklet 2020-21:
- RET survey of Jamtara and Dumka via Nala new line – 75 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
605% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 3221 Cr/ Rs. 457 Cr.)
Karnataka:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
- New line between Belgaum to Dharwad via Kittur of Length 73.1 Km, Costing ₹988.3 Cr.
Survey works included in Budget Booklet 2020-21:
- PET survey of Talaguppa and Hubbali via Siddapur, Sirsi Mundgod and Tadas new line- 158 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
404% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4212 Cr/ Rs. 835 Cr.)
Kerala:
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
85% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 688 Cr/ Rs. 372 Cr.)
Maharashtra:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- Long pending bypass connectivity line named Daund Chord line(1.025 Km) on Daund-Manmad route completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
02 Projects of total 939 Km length, costing Rs. 8745 Cr. have been included, as per below details:
- Doubling of Akola- Dhone via Purna, Mudhkhed, Secunderabad, Mehboobnagar excluding Purna-Mudkhed and Bolarum-Mehboobnagar including Dhone bye pass of Length 626 Km, Costing ₹6260 Cr.
- Bhusawal-Wardha 3rd line of Length 313 Km, Costing ₹2485 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
472% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 6700 Cr/ Rs. 1171 Cr.)
Madhya Pradesh:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- Bypass line(2 Km long) named Jukhei Chord line, bypassing the Katni yard in Madhya Pradesh, costing Rs.12 cr got completed & commissioned.
Survey works included in Budget Booklet 2020-21:
- RET survey of Khandwa-Dhar via Kharegone and Barwani new line – 260 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
930% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 6509 Cr/ Rs. 632 Cr.)
Odisha:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
02 Projects of total 266 Km length, costing Rs. 3,663 Cr. have been included as per below details:
- New line between Kiriburu to Barbil of Length 24.5 Km, Costing ₹705.17 Cr.
- New line from Sambhalpur to Gopalpur via Phulbani of Length 241 Km, Costing ₹2957.44 Cr
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
532% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 5296 Cr/ Rs. 838 Cr.)
Punjab:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
02 Projects of total 921 Km length, costing Rs. 9210 Cr. have been included, as per below details:
- Doubling of Firozpur- Bhatinda and Jakhal- Hisar of Length 168.8 Km, Costing ₹1688 Cr
- Doubling of Bhatinda- Bhildi via Sirsa, Hisar, Ratangarh, Degana, Luni, Samdhari excluding Degana- Rai ka Bag of Length 752.2 Km, Costing ₹7522 Cr
Survey works included in Budget Booklet 2020-21:
- Updating survey of Garhshankar-Sri Anand Sahib new line – 49 Km
- Updating survey of Rahon-Samrala new line – 36.56 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
595% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 1565 Cr/ Rs. 225 Cr.)
Rajasthan:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
04 Projects of total 429Km length, costing Rs. 1748Cr. have been commissioned, as per below details:
- 58.5 Km long New Line project from Thaiyat Hamira-Sanu, costing Rs.325 cr. got completed & commissioned in all respect.
- 320 Km long Gauge Conversion Project from Jaipur-Ringus-Sikar-Churu & Sikar-Loharu, costing Rs.1116 cr. got completed & commissioned in all respect.
- 26 Km long Doubling project from Abu Road to Swaroop Ganj, costing Rs.176 cr. completed & commissioned.
- 24 Km long Doubling project from Abu Road to Sarotra Road, costing Rs.131 cr. completed & commissioned
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
04 Projects of total 979 Km length, costing Rs. 10,100 Cr. have been included as per below details:
- Doubling of Bhatinda- Bhildi via Sirsa, Hisar, Ratangarh, Degana, Luni, Samdhari excluding Degana- Rai ka Bag of Length 752.2 Km, Costing ₹7522 Cr.
- Doubling of Ajmer- Chittorgarh of Length 186 Km, Costing ₹1860 Cr.
- Bypass line at Sawaimadhopur of Length 6.98 Km, Costing ₹252 Cr.
- Dedicated Test Track for RDSO (Phase-II) of Length 34 Km, Costing ₹466.42 Cr
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
572% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 4581 Cr/ Rs. 682 Cr.)
Tamil Nadu:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
06 Projects of total 826 Km length, costing Rs. 8501 Cr. have been included, as per below details:
- Doubling of Katpadi- Villupuram of Length 160.1 Km, Costing ₹1601 Cr
- Doubling of Salem- Karur- Dindigul of Length 160 Km, Costing ₹1600 Cr
- Doubling of Erode- Karur of Length 65 Km, Costing ₹650 Cr.
- Doubling of Dharmavaram- Pakala- Katpadi of Length 290 Km, Costing ₹2900 Cr.
- Doubling of Hosur- Omalur of Length 147 Km, Costing ₹1470 Cr
- Doubling of Chennai Beach- Chennai Egmore of Length 4.3 Km, Costing ₹279.8 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
220% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 2812 Cr/ Rs. 879 Cr.)
Telagana:
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
02 Projects of total 874 Km length, costing Rs. 8740 Cr. have been included, as per below details:
- Doubling of Guntur- Bibinagar of Length 248 Km, Costing ₹2480 Cr.
- Doubling of Akola- Dhone via Purna, Mudhkhed, Secunderabad, Mehboobnagar excluding Purna-Mudkhed and Bolarum-Mehboobnagar including Dhone bye pass of Length 626 Km, Costing ₹6260 Cr
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
Budget out lay of Rs 2602 Cr has been proposed in FY 20-21
Uttarakhand:
Survey works included in Budget Booklet 2020-21:
- FLS for doubling of Dehradun-Haridwar – 52 Km
- PET survey for doubling of Raiwala-Rishikesh – 12 Km
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
852% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 1780 Cr/ Rs. 187 Cr.)
Uttar Pradesh:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
- 55.47 Km long Doubling work in UP from Meerut-Muzaffarnagar, costing ₹ 439 Cr. got completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
04 Projects of total 298 Km length, costing Rs. 3815 Cr. have been included as per below details:
- Doubling of Moradabad- Chandausi of Length 44 Km, Costing ₹440 Cr.
- Doubling of Billi- Chunar of Length 108 Km, Costing ₹1080 Cr.
- Doubling of Gorakhpur- Valmikinagar of Length 87 Km, Costing ₹992.7 Cr.
- New line between Hardoi to Gursahaiganj via Sandi of Length 59.3 Km, Costing ₹1302.13 Cr
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
673% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 8576 Cr/ Rs. 1109 Cr.)
West Bengal:
Complete Projects (falling partly/fully in the state) commissioned during 2019-20:
04 Projects of total 15Km length, costing Rs. 217 Cr. have been commissioned as per below details:
- Double line bypass connectivity (2.86 Km long) work joining double line track (Asansol-Raurkela & Asansol-Bardhaman), got completed & commissioned in West Bengal.
- 1.67 Km long doubling project named New Alipore-Mile 5B in Sub-urban area of Sealdah, costing ₹ 65 Cr.got completed & commissioned in West Bengal.
- 7 Km long Doubling project from Andul-Baltikuri, costing ₹ 89 Cr.got completed & commissioned.
- 3 Km long Mohishila-kallipahari link doubling project, costing Rs 43 Cr. completed & commissioned.
Projects (falling partly/fully in the state) included in Budget Booklet 2020-21 (against Umbrella work of 2019-20):
- Doubling of Katihar- Kumedpur and Katihar- Mukuria of Length 64.5 Km, Costing ₹645 Cr.
Proposed Budget outlay FY 20-21 for infrastructure & safety works falling fully/partly in the state:
20% more outlay in FY 20-21 w.r.t average annual outlay during 2009-14 (Rs. 5246 Cr/ Rs. 4380 Cr.)