Major Progress in Wardha-Ballarshah New 3rd Line Project Enhances Rail Connectivity
In a noteworthy development, the Wardha-Ballarshah New 3rd Line project has seen significant advancements, showcasing its impact on the rail infrastructure in the region. Here are the key details:
- Project Cost: The project has been estimated at ₹1384.72 Crores, with an expenditure of ₹833.49 Crores till date.
- Physical Progress: Overall progress stands at an impressive 67%.
- Total Length: The new 3rd line spans a total length of 132.34 km, with 29.35 km already commissioned.
- Land Acquisition: A substantial 70% of the land acquisition process has been completed, covering 125.52 out of 136.44 hectares.
Project Sections Breakdown:
A) Completed Sections (25.18%):
- Wardha to Hinganghat (33.33 km)
B) Near Completion Sections (36.25%):
- Hinganghat to Chikni Road (47.98 km)
- Majri to Tadali
C) Sections in Progress (38.57%):
- Chikni Road to Majri (51.03 km)
- Tadali to Ballarshah
Ongoing Works:
- Earthwork: 58.73% completed (15.16/25.81 Lcum)
- Blanketing: 30.76% completed (60,000/195,000 Cum)
- Important Bridges: 50% completed (1/2)
- Major Bridges: 6 out of 12 in progress
- Minor Bridges/LHS/RUB: 14.68% completed (21/146)
- Station Buildings: 26.30% completed (5/19)
- Track Linking: 22.18% completed (30/132 Tkm)
- Overhead Equipment (OHE) Foundations: 22% completed (620/2904)
- OHE Mast Erections: 14% completed (368/2640)
- OHE Wiring: 11% completed (15/132 km)
- Signalling and Telecommunication Works: 16% completed (3/18)
Project Impact: The completion of this new 3rd line will significantly alleviate congestion on the busy Secunderabad-Wardha-Nagpur route, enhancing overall train mobility in the region.