Major Milestone Achieved: Daund – Manmad Doubling Project Progress Update

In a significant development, the Daund – Manmad Doubling Project has achieved notable progress, marking a crucial step towards enhancing rail infrastructure. Here are the key details:

  • Total Length: The project spans a total length of 236.61 km.
  • Length Commissioned: A substantial 134.31 km has already been commissioned.
  • Remaining: With 102.3 km left to complete, the overall physical progress stands at an impressive 78%.

Financial Overview:

  • Cost: The estimated cost of the project is ₹2081.27 Cr.
  • Expenditure till Date: An expenditure of ₹1624.53 Cr has been incurred.

Project Phases:

  1. Completed Doubling: Covering 134.31 km (56.76%)
    • Manmad – Kanhegaon
    • Visapur – Kashti
    • Akolner – Sarola
    • Puntamba – Padhegaon
  2. Near Completion: Encompassing 48.26 km (20.40%)
    • Padhegaon – Nimblak
  3. In Progress Section: Extending over 54.04 km (22.84%)
    • Nimblak – Akolner
    • Kanhegaon – Puntamba
    • Kashti – Daund
    • Sarola – Visapur

Key Project Metrics:

  • Land Acquisition: 13.57 / 68.165 Hectare (19.9%)
  • Completed Works Details:
    • Earthwork: 122.20 / 162.043 Lcum (75%)
    • Blanketing: 2.48 / 4.00 cum (62%)
    • Important Bridges: 1 completed, 4 in Progress (18%)
    • Major Bridges: 13 / 28 (46%)
    • Minor Bridge/LHS/RUB: 101 / 117 (86%)
    • Station Building: 11 / 21 (52%)
    • Track Linking: 156.03 / 289.643 Track km (54%)
    • OHE (Overhead Equipment) Foundation: 2400 / 6000 (40%)
    • OHE Mast Erections: 2000 / 4800 (42%)
    • OHE Wiring: 289.64 / 150.00 Track km (52%)
    • New Signalling Electronic Overlocking: 6 / 22 Stations (27%)
    • Signalling Indoor and Outdoor Works: 16 / 36 (44%)

Impact and Benefits: The completion of the Daund – Manmad Doubling Project is poised to significantly enhance train mobility, alleviating congestion in the section. This achievement marks a substantial advancement in the region’s rail infrastructure, promising improved efficiency and reduced transit times.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.