Major Infrastructure Boost in Ahmednagar-Beed-Parli Vaijnath New Rail Line Project

Ahmednagar: In a significant development, the Ahmednagar-Beed-Parli Vaijnath new rail line project is making substantial progress, with an investment of ₹4805.17 Crores. The joint funding initiative from the Central Railway and the State Government, with a 50:50 ratio, underscores the commitment to enhancing regional connectivity.

Financial Update: With an expenditure of ₹3759.40 Crores to date, the project has reached an impressive overall physical progress of 80%. The extensive 261.25 km length of the new rail line has seen notable achievements, particularly in land acquisition, where 99.15% of the targeted 1821.65 hectares have been secured.

Section-wise Progress:

A) Completed Section: The stretch from Ahmednagar to Ashti covering 66.18 km is fully operational, marking a significant milestone in the project.

B) Near Completion Section: The Ashti to Eganwadi section, covering 67.12 km, is poised to be completed by the end of the current financial year.

C) In Progress Section: The remaining segment from Eganwadi to Parli is actively under construction.

Ongoing Works:

The project is witnessing commendable progress in various aspects:

  • Earthwork completion stands at an impressive 97% (419.88/430.43 Lcum).
  • Important bridges/Major Bridge construction is at 91% completion (58/64).
  • Minor Bridges development has reached 84% (301/252).
  • Ballast supply is at 88% (6.603/7.52 Lcum).
  • Progress in ROB/RUB construction is at 66% (128/195).
  • Station Building development is at 30% (6/21).
  • Signaling and telecom works are ongoing at 10 stations.
  • Track Linking progress is at 43% (124.32/285.89 track km).
  • Power line crossing completion stands at 91% (568/626).
  • Electrification is in progress for the entire 261.25 km stretch.

Regional Impact:

The successful completion of this new rail line is anticipated to significantly enhance connectivity in the Marathwada region, providing a vital transportation link for both passengers and goods.

Central Railway’s Overall Progress:

Across its five divisions, Central Railway has demonstrated a robust commitment to infrastructural development:

  • Completion of 161.80 km of multitracking (new line/doubling/3rd/4th line) has been achieved from April 2023 to the present.
  • A planned investment of ₹3890 Crores for new lines/doubling/3rd/4th line projects is in progress, with ₹2990 Crores already expended.

The Ahmednagar-Beed-Parli Vaijnath new rail line project is a testament to the collaborative efforts of the Central Railway and the State Government in bolstering transportation infrastructure and regional connectivity.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.

Related Articles

Back to top button