ECoR Achieves Breakthrough Connecting Escape Tunnel with Longest Tunnel in Khurda Road-Balangir Rail Line Project
In a significant advancement, the East Coast Railway (ECoR) has achieved a milestone in the Khurda Road-Balangir Rail Line Project by successfully connecting a 700-meter escape tunnel with the 4185-meter longest tunnel in the Adhenigarh-Charichhak Section. This breakthrough, accomplished under the deep reserve forest of Madhapur Forest Range, marks a crucial phase in enhancing connectivity through remote regions of Boudh District.
The Khurda Road-Balangir Rail Link Project, spanning 301 kilometers, is a pivotal infrastructure initiative aimed at boosting connectivity across Odisha. Currently, 152.805 kilometers of the project have been commissioned, with intensive efforts underway to expedite completion.
Focus on Early Completion:
The railway authorities have prioritized the early completion of ongoing projects, including the Khurda Road-Balangir line. Construction efforts are being meticulously executed from both Khurda Road and Balangir ends to expedite the project’s timeline.
Project Milestones:
- Completed Sections: As of now, 105.8 kilometers from Khurda Road to Daspalla and 47 kilometers from Balangir to Sonepur have been successfully commissioned.
- Upcoming Completion: The segment from Sonepur to Jharmunda, covering 28.765 kilometers, has also been completed. Furthermore, the stretch from Sonepur to Purunakatak, totaling 73 kilometers, is slated for completion in the coming months.
Strategic Importance:
The Khurda Road-Balangir project holds immense strategic importance, especially in connecting remote and underserved areas. The Ministry of Railways has been closely monitoring its progress to ensure timely completion, emphasizing its public-centric approach and the transformative impact on regional connectivity.
Future Outlook:
With construction efforts proceeding from multiple fronts, the Railways aims to meet its targeted timeline for the entire project. This approach not only accelerates development but also underscores the commitment to enhancing rail connectivity across Odisha.
The breakthrough achievement at the Adhenigarh-Charichhak Section represents a significant step forward in the ambitious Khurda Road-Balangir Rail Line Project. As construction progresses, stakeholders anticipate further milestones that will bring enhanced connectivity and economic opportunities to the region.