Central Railway Successfully Completes and Commissions 23.69 km New Line Section on Wardha-Nanded Route

Mumbai, December 23, 2023: The Central Railway (CR) has achieved a significant milestone by successfully completing and commissioning a new 23.69 km line section between Deoli and Kalamb on the Wardha-Nanded route. The Commissioner of Railway Safety (CRS), Manoj Arora, conducted a thorough inspection of the newly opened line sections and granted it a safety certificate. A successful speed trial of 125 kmph was also conducted on the freshly inaugurated line.

Chief Administrative Officer Construction, Shri. Avanish Kumar Pandey, and Divisional Railway Manager (DRM) of Nagpur, Shri. Tushar Kant Pandey, also conducted inspections of the new line. With the opening of this 23.69 km section, CR has completed the construction of 185.49 km of new lines, double lines, and 3rd/4th lines between April and December 2023.

Wardha-Nanded New Line (via Yavatmal-Pusad) – Nagpur Division:

  • Length: 284.65 km
  • Overall Physical Progress: 47%
  • Cost: ₹3445.48 Cr
  • Expenditure till date: ₹1910.07 Cr
  • Funding Pattern: Railways (60%), State Govt (40%)
  • Land Acquisition Completed: 1911/2138 Hectare (89%)
  • Total Stations: 26
  • Completed Stations: 4

Completed Section:

  • Wardha-Kalamb: 38.61 km

In Progress Sections:

  • Kalamb-Nanded: 246.05 km

In Progress Works:

  • Earthwork: 87.54/201.14 Lcum (44%)
  • Formation: 40/284.60 km
  • Major Bridges: 32/80 completed
  • Minor Bridges: 50/320 completed
  • Road over Bridge (ROB): 43 In Progress
  • Road under Bridges (RUB): 19/52 completed
  • Station Buildings: 4/26
  • Tunnels: 6 in progress of total 8 km length
  • Track Linking: 40/284.60 km

The completion of this new line is expected to enhance connectivity in the Vidarbha and Marathwada regions, benefitting districts such as Wardha, Yavatmal, Washim, and Nanded.

Key Achievements:

  • CR completed 185.50 km of new lines, doubling, 3rd/4th lines from April ’23 to date.
  • ₹3887 Cr planned for new lines, doubling, 3rd/4th lines this year by CR.
  • ₹3006 Cr expenditure completed till date, accounting for 77% of the planned budget.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.