Daund-Manmad Doubling Project: Enhancing Rail Connectivity and Efficiency

In a significant development, Central Railways (CR) has made substantial progress in the Daund-Manmad Doubling Project, contributing to improved rail connectivity and efficiency.

Key Achievements:

  • In the current fiscal year (from April 2023 to date), CR has successfully completed 147.77 km of multi-tracking, which includes new lines, doubling, third and fourth lines.
  • A substantial budget of Rs 3,886.95 Crores has been allocated for the fiscal year to support new lines, doubling, third and fourth lines, and gauge conversion projects.
  • As of now, an expenditure of Rs 2,983.47 Crores has been incurred, reflecting 76% utilization of the allocated funds.

Daund-Manmad Doubling Details:

  • The Daund-Manmad Doubling Project spans a length of 236.61 km.
  • An impressive 120.28 km (50.83%) of the doubling work has already been completed, leaving 116.33 km (49.16%) to be finished.
  • The estimated cost of this project is Rs 2,081.27 Crores, with an expenditure of Rs 1,572.28 Crores incurred to date.
  • The overall physical progress stands at an impressive 65%.

Notable Achievements:

A) Completed Doubling – 120.28 km (50.28%):

  • Kashti-Belwandi
  • Sarola-Akolner
  • Padhegaon-Puntamba
  • Kanhegaon-Manmad

B) Near Completion Section (Likely commissioning this financial year) – 62.29 km (26.32%):

  • Nimblak-Padhegaon
  • Belwandi-Visapur

C) In Progress – 54.04 km (22.83%):

  • Daund-Kashti
  • Visapur-Sarola
  • Akolner-Nimblak
  • Puntamba-Kanhegaon

Land Acquisition Progress:

  • Land acquisition required: 68.16 Hectare.
  • Land acquisition completed: 13.14 Ha (20%)
  • Land acquisition remaining: 55.02 Ha (80%)

Detailed Progress in Completed Works:

  • Earthwork: 116.87/162.04 lakh cum (72%)
  • Blanketing: 2.4/4.0 Cum
  • Major bridges: 11/28 (39%)
  • Minor bridges/Road Under Bridges: 100/117 (86%)
  • New station buildings: 11/21 (52%)
  • Track linking: 154/290 track km (53%)
  • OHE (Overhead equipment) Foundations: 2400/6000 (40%)
  • OHE Mast erection: 2000/4800 (42%)
  • OHE Wiring: 150/290 track km (52%)
  • Signalling New Electronic Interlocking: 6/22 stations (27%)
  • Signalling indoor & outdoor works: 16/36 (44%)

The completion of the Daund-Manmad section doubling work will greatly enhance train mobility, reduce train crossing detention time, and alleviate congestion in the section, ultimately benefiting passengers and the transportation of goods.

Siddharatha

A proficient tv reporter with excellent researching skills. I'm adept at telling stories filled with scientific fervour. Stories which are useful for our viewers and enabling them to get real insight for their life. Experienced in tv reporting with more than 17 years of rich experience with leading news channel AajTak. A varied experience of telling news stories, editing articles, covering events and interviewing celebrities across myriad beats like environment, science, climate, weather, disaster, railways, agriculture, socially-relevant topics and human interest stories. Both as a team-player and as an individual my goal has always been, and shall remain, to adhere to deadlines without compromising on quality with the sole aim to grow as an individual by following journalistic ethics and humanity.